Project Details
Introduction
This project was a full lift replacement for a low density condominium in Singapore with four lifts, one per block. The lifts were more than 30 years old and at the end of their working life. We began in August 2026 and completed all four replacements in October 2026, a total of 12 weeks.
The Challenge
Problem
The management council was dealing with an increasing frequency of lift breakdowns. Each time a lift failed, the recovery time was getting longer, moving from a few days to one to two weeks, and the cost of each repair was getting higher.
Because there is only one lift per block, every breakdown left the residents of that block without a lift, which caused real inconvenience. Residents were very frustrated with the constant breakdowns and had lost confidence in their existing lift service provider to put the problems right.
The management council was also told that the existing lift model and system were obsolete, so there were no more spares available to repair the lifts. That left full modernisation as the only viable solution.
The council tasked their managing agent to find alternative solutions and to compare them with their existing lift provider. The managing agent found us, Hin Chong, through a Google search and contacted us for help. We visited the site for a non-obligatory survey, gave an unbiased assessment of the condition of the lifts, and set out the options, from a simple partial lift modernisation to a complex full lift replacement, with the pros and cons of each. We were awarded the project because of our professionalism and our honest, unbiased proposal.
Solution
We recommended a full lift replacement. The lift model was over 30 years old and the interior condition of the lifts was dilapidated. Over the long term, a full lift replacement was the most cost effective and cost efficient solution.
Because there is only one lift per block, we were aware of how much residents would feel the loss of a lift during the works. We have wide experience of lift modernisation in developments with one lift per block, and we were confident of completing each full lift replacement in 4 weeks. Our main objective was to shorten the modernisation period.
The work we carried out:
- A survey and assessment of all four lifts before work began
- A comparison of partial modernisation against full replacement for the council
- Full replacement of each of the four lifts, including the lift interior
- Removal of the obsolete lift system and installation of a current model with spares available
- Phased work block by block, so each block had its new lift back in service before we moved on
- Testing and handover of each lift before it returned to daily use
In the end we completed the four full lift replacements in 12 weeks, or 3 weeks per lift, on average one week faster than the 4 weeks we had promised. The management council, the managing agent and the residents were delighted with the dedication, professionalism and service of our team, and were thankful for the extra effort that got each lift replaced in less than 4 weeks.
None of this would have gone so smoothly without the cooperation of the managing agent and the council, and the understanding of the residents. The credit for the success of this project goes to everyone.
Key Results and Outcomes
- Long term savings on lift repairs and maintenance
- Property enhancement to increase the value of the development
- Elimination of lift obsolescence, with a current system and spares available again
- Greatly improved lift reliability, comfort and aesthetics
Conclusion
The four lifts were replaced in 12 weeks between August and October 2026, ahead of the schedule we had set for each lift. A development that had lived with constant breakdowns and obsolete lifts now has four reliable new lifts, a better experience for residents and lower long term costs. We are grateful for the trust the council, the managing agent and the residents placed in us.
What the client said
Had 4 brand new lift replacement for a 30 years old estate. Due to budget constraints, estate had to go through multiple lift vendors until finally getting to know Hin Chong. 1. Prices were transparent 2. Had been duly notified and informed step by step along the replacement. Communication top notch. 3. Initially planned for a 5 months replacement for 4 lifts. They manage to resolve and changed everything within 3 months. 4. Quick to rectify any works even after completion. I am very glad with them and highly recommend their services. Look for Adrian. I can assure he resolves your problems.
Benjamin Liew